Lewes & Eastbourne Council Raffan Court - CASE STUDY
Background
CLIENT BRIEF
As the units become available, Amstech were commissioned to remove all asbestos from within the units to allow for refurbishment.
CLIENT BRIEF
As the units become available, Amstech were commissioned to remove all asbestos from within the units to allow for refurbishment.
Services
Asbestos removal to dwellings within the sheltered/assisted housing block
INDUSTRY SECTOR
Council/Housing
Asbestos removal to dwellings within the sheltered/assisted housing block
INDUSTRY SECTOR
Council/Housing
PROJECT DURATION
1 day – 1 week per unit – on-going
PROJECT VALUE
£2k – £5k per unit
PROJECT SOLUTION
Ensuring sufficient Labour and plant were available so as not to delay
the completion of units and to allow for follow-on trades to complete
their works in a timely manner.
PROJECT RESULT
To date all units have been completed on time to allow the units to be refurbished and
re-let to new tenants so helping to meet all KPIs.